Deconstructing a dam

Decade-long Matilija effort may face new funding hurdles


By Laura Mecoy
Sacramento Bee
October 4, 2005

LOS ANGELES - A recent vote to provide $2 million in state funds to develop final plans for tearing down the Matilija Dam moved this long-awaited ecological restoration program one step closer to reality.

But the cost of recovery from Hurricanes Katrina and Rita could cause even further delays in a decade-long fight to demolish a dam that has wreaked its own havoc on Ventura County's beaches and steelhead populations.

At 198 feet at its highest point, the Matilija Dam, located near the Ventura River's headwaters northwest of Ojai, is one of the largest dams ever considered for removal.

Tearing it down would set a precedent for future dam removals and add fuel to a growing movement to restore habitat and fisheries by eliminating these structures blocking America's rivers and streams.

"This is something that, hopefully, is going to lead the way and show some of the mistakes we have made in the past can be repaired and we can get back some of the natural assets of these rivers that have been lost," said Paul Jenkin, Matilija Coalition program coordinator.

Around the country, 185 dams have been removed since 1999, and 56 more are slated for demolition this year, according to the advocacy group American Rivers. Most are much smaller than the Matilija (pronounced Ma-til-a-ha).

The $2 million that the California Ocean Protection Council recently agreed to provide to the Matilija Dam project would help pay for the engineering plans to remove the structure and accommodate a free-flowing river.

Another $4 million in federal money is needed for the engineering, and the federal government is supposed to pay most of the $130 million bill for construction and removal.

But the enormous cost of repairing levees and other water-related projects destroyed by the two recent Gulf Coast hurricanes is expected to soak up most of the available water project money for years to come.

"The funding situation is going to be really tight moving forward for all kinds of restoration projects," said Elizabeth Maclin, director of the American Rivers dam removal program.

Even so, Assemblyman Pedro Nava, D-Santa Barbara, said the state should continue on the Matilija project.

"We have a facility that doesn't serve any purpose other than retaining sediment that ought to be on the beaches," he said.

The 58-year-old Matilija Dam no longer provides much water supply or flood control because 6 million cubic yards of silt, gravel and dirt have collected behind it.

Its face is laced with cracks because it was built with faulty materials. Construction crews removed part of the concrete along the top of the structure in 1965 and again in 1978 to guard against a potential collapse.

The dam blocks the southern steelhead trout from some of its best spawning grounds, contributing to the steep decline in populations that caused the native fish to be declared a federally endangered species in 1997.

The Army Corps of Engineers, in its studies of the project, said the Ventura River once supported 4,000 to 5,000 spawning adult steelhead, and now it supports just 100. The study said removing the Matilija Dam would open up more than 17 miles of steelhead habitat.

Demolishing the dam would also restore eroding Ventura County beaches by freeing up trapped sand and gravel and restoring its natural flow to the shore, the Corps of Engineers said.

The agency determined about 4 million cubic yards of sand, gravel and sediment would flow into the Ventura River and onto the Ventura County beaches after the dam's removal. It estimates the beaches and the riverbed would be restored to their pre-dam states within 10 years of the dam's destruction.

"The Matilija Dam removal is unusual in that aspect," American Rivers' Maclin said. "You don't often see a river carrying that amount of sand."

Tearing down the dam without any other action would cause a catastrophic flow of silt and sand into the river, especially in a region where there are long periods of drought followed by flash floods.
So the Corps of Engineers plans to remove a third of the 6 million cubic yards of sediments behind the dam.

It then plans to carve a 100-foot channel and place the sand and gravel on the banks. The agency expects the river would carry these sediments downstream over a 20-year period.

To guard against downstream flooding, the corps' plan calls for building levees along portions of the Ventura River and modifying some bridges. Plus, it plans to build eight miles of recreational trails and two groundwater wells to replace lost water supplies.

The project is supposed to be completed in 2012, but funding delays could push it further into the future.

These types of dam removals have been gaining ground around the country as more of these structures reach the end of their estimated 50-year life spans. About a quarter of the 75,000 structures on the nation's dam inventory are more than 50 years old, and 85 percent will reach that age by 2020, according to American Rivers.

"At Matilija, we are doing something that has never been done before," Jenkin of the Matilija Coalition said. "In terms of its precedent and what it is going to accomplish for this watershed and other watersheds, it is a huge project."



Copyright 1999-2005, California Coastal Coalition
Phone: (760) 944-3564